Project Overview

Baptist Health Lexington Simulation Center Development

Phase 1 Planning
Phase 1 CAPEX
$2.6M
5-Year Total:$4.5M
Timeline
12 Months
15%
Staffing (FTE)
2.5

Core staff + 20% faculty allocation

Risk Status
22 Identified

8 high priority requiring attention

Budget Allocation
Phase 1 capital and equipment investment breakdown
Construction$1.5M

Facility renovation & buildout

Equipment$388K

Simulators & task trainers

A/V System$90K

Recording & debriefing systems

Contingency$241K

10% reserve

Total Phase 1 Investment
$2.6M
Open Budget Simulator
Project Timeline
12-month implementation from design to go-live

Planning & Design

Month 1-3

Active

Procurement & Bidding

Month 4

Pending

Construction

Month 5-8

Pending

Systems Installation

Month 9

Pending

Staff Training

Month 10

Pending

Go-Live

Month 11

Pending
Top Risks
Highest priority risks by score
8

Unauthorized Access or Disclosure

security

mitigating
6

Unforeseen Hazardous Materials

Environmental

identified
6

IT Network & System Integration Issues

Technical

identified
6

Equipment Procurement Delays

Procurement

identified
View all 22 risks

Phase 1: 3-Room Simulation Center

4,000 SF facility with 2 high-fidelity manikins

3
Simulation Suites
1
Control Room
2
Debrief Rooms
12
Months to Go-Live